2023 Smoke Testing

The following streets were included in the 2023 Smoke Testing Program:
Blackburn, Brown, Louisiana, May, Norwood, Oris, Rainey, Speed, Summit,
Talley, Van Zandt, and West
Frequently Asked Questions:
Have other questions or need additional information? Call the Public Works department at (903) 935-4516.
2023 Street Improvement Program
This includes the complete reconstruction, paving, striping, and signage upgrades of select City of Marshall streets.
Phase One: Overlay
Below is the updated chart of the 2023 Street Improvement Project. As of July 2023, 69% of roads are completed (17,940 feet of 25,940 feet total). The anticipated completion date is mid-August.

Phase Two: Reconstruction (work to begin late July/early August 2023)