Current Projects

2023 Smoke Testing

Smoke Testing Graphic

The following streets were included in the 2023 Smoke Testing Program:

Blackburn, Brown, Louisiana, May, Norwood, Oris, Rainey, Speed, Summit, 

Talley, Van Zandt, and West




Frequently Asked Questions:

Have other questions or need additional information? Call the Public Works department at (903) 935-4516.



2023 Street Improvement Program

This includes the complete reconstruction, paving, striping, and signage upgrades of select City of Marshall streets.

Phase One: Overlay

Below is the updated chart of the 2023 Street Improvement Project.  As of July 2023, 69% of roads are completed (17,940 feet of 25,940 feet total).  The anticipated completion date is mid-August.

July 17 Road Construction Update

Phase Two: Reconstruction (work to begin late July/early August 2023)